As weather permits work continues on the construction of Station #2. The block work for the last front doorway is complete. All six bays are now visible from the front of the building. Brick work around the door openings continues. Blocks are in place to provide support for the 2nd floor steel which is now being installed. Work to install the 2nd floor stairs and the corrugated metal needed to allow for the second floor concrete pour should continue this week. Once the steel is completed the concrete pour for the 2nd floor will start, block and brick work will continue with roof trussing will follow.